Procedure for the Site Assembly and Installation of 1600mm x 1200mm Left Hand Single Exit Landing and Staircase Flight

Table of Contents

Preparation Notes

  • This document should be read in conjunction with the appropriate standard installation procedures for single and double stacked steel units via crane or HIAB.
  • This procedure requires a minimum of two suitably qualified and competent personnel at all times.
  • The installation team should ensure that they are fully conversant with all aspects of this procedure and the detailed assembly diagrams overleaf prior to the commencement of work.
  • The installation team should ensure that safe handling techniques are adopted at all times.
  • Alsim System Buildings Limited will not be held responsible for any incident, accident or injury, resulting from the installation of a landing, staircase or related item, as described herein

Suggested Basic Safety Equipment

Suggested Basic Safety Equipment

  • Safety Boots
  • High Visibility Clothing
  • Hard Hat
  • Protective Gloves suited to this application
  • Safety Eyewear

Tools & Equipment Required

Tools & Equipment Required

  • Crane or HIAB
  • Ladder
  • Socket Set to suit fixings listed below
  • Spirit Level

Parts Check List

  1. Staircase Assembly, item 1 (x1)
  2. Landing Support Leg, item 2 (x2)
  3. Brace Bar, item 3 (x1)
  4. Handrail Assembly, item 4 (x2)
  5. Landing Platform Assembly, item 5 (x1)
  6. Landing Handrail Assembly, item 6 (x1)
  7. Landing Handrail Assembly, item 7 (x1)
  8. M12 x 80mm M/S Bolt (x4)
  9. M12 x 50mm M/S Bolt (x3)
  10. M12 x 30mm M/S Bolt (x4)
  11. M12 M/S Nut (x7)
  12. M12 Flat M/S Washer (x18)

Step by Step Instructions

  1. The staircase can be hung from the left of the landing only. The diagrams overleaf illustrate a landing of dimensions 1600mm x 1200mm, and the following procedure applies to this size only.
  2. Position Landing Handrail Assembly (Item 7) into locating sockets on Landing Platform (Item 5), making sure the kick plate is on the inside of the landing (see Figure 2). Secure by tightening the pre-installed bolts.
  3. Position Landing Handrail Assembly (Item 6) into locating sockets on Landing Platform (Item 5), making sure the kick plate is on the inside of the landing (see Figure 3). Secure by tightening the pre-installed bolts.
  4. Lift Landing Assembly, created by steps 2 and 3 above, into position using a suitable crane or HIAB.
  5. Position both Landing Support Legs (Item 2) into locating sockets (see Figure 4). Please note that the Landing Support Legs are adjustable to suit ground conditions.
  6. Locate Landing Assembly, created by steps 2 and 3 above, to the Top Stacked Unit (see Figure 5) using the unit’s integrated staircase bracket. Secure using the designated fixings. This step will require the use of a ladder to reach the underside of the Landing Assembly. The ladder must be footed, or otherwise secured to avoid slippage, at all times.
  7. Ensure Landing is level using a spirit level prior to final fixing.
  8. Secure both Landing Support Legs (Item 2) into position using designated fixings (see Figure 4).
  9. Locate Brace Bar (Item 3) between both Support Legs (Item 2) (see Figure 6). Secure using the designated fixings.
  10. Fit both Handrails (Item 4) into locating sockets on the outer side of Staircase Assembly (see Figure 7) and secure by tightening the pre-installed bolts.
  11. Lift Staircase Assembly (Item 1) into position using a suitable crane or HIAB.
  12. Locate Staircase Assembly (Item 1) to Landing Platform (see Figure 8) using the three locating points on the Landing Platform. Secure using the designated fixings. This step will require the use of a ladder to reach the underside of the Landing Assembly. The ladder must be footed, or otherwise secured to avoid slippage, at all times.

Image